The Japan International Cooperation Agency (JICA) signed a Loan Agreement (L/A) with the Government of India for two projects totaling up to 40,673 million yen on February 27 in Delhi.
The two projects covered by the yen loan agreements signed this time are as follows.
(1) Mumbai Bay Crossing Road Construction Project (Phase III) (Loan amount: 30,755 million yen)
(2) Mizoram State Advanced Specialized Cancer Research Center Establishment Project (Loan amount: 9,918 million yen)
Details of each business are as follows
(1) Mumbai Trans-Harbour Link Project (Phase III)
(a) Purpose and outline of business
This project will construct an 18-km-long marine road and a 4-km-long land approach road in the Mumbai metropolitan area in Maharashtra, connecting central Mumbai on the peninsula side with the Navi Mumbai area on the eastern suburbs across the Mumbai Bay. This will improve connectivity to the Navi Mumbai area, where urban development is planned, and contribute to further economic growth by promoting regional economic development, thereby contributing to SDGs (Sustainable Development Goals) Goals 8, 9, 11, and 13.
(b) Project implementing agency
Mumbai Metropolitan Region Development Authority
Address: M.M.R.D.A. Office Building, Bandra Kurla Complex, E Block, MMRDA Building, C-14 & 15, E Block Bandra (East), Mumbai, Maharashtra 400051
Phone/Fax: +91-22-2659-4034(4179)
(c) Schedule for future project implementation (tentative)
- Scheduled completion of the project: September 2023 (the project will be completed when the facilities are put into service)
-
Expected date of sending invitation letter for consulting services (construction supervision, etc.): Hired
-
Publication of bids for the first procurement package through international competitive bidding for the main body of work: Civil Engineering Package (Construction Works): Contracted.
(2) Project for the Establishment of Mizoram State Super-Specialty Cancer and Research Centre
(a) Purpose and outline of business
This project aims to establish a state cancer research center in Mizoram, a state with a particularly high cancer incidence and mortality rate in India, and to build a cancer system in the state centered on the center. The project will provide sufficient access to cancer prevention, screening, and treatment for the residents of the state, and promote human resource development and research to support cancer control in the state, thereby contributing to the strengthening of the state’s cancer health care system and contributing to Goal 3 of the SDGs (Sustainable Development Goals).
(b) Project implementing agency
Government of Mizoram, Health and Family Welfare Department
Address: Mizoram Secretariat, Building No. 1 MINECO, Khatla, Aizawl, Mizoram. 796001
Phone/Fax: +91-389-2322532
(c) Schedule for future project implementation (tentative)
Scheduled completion of the project: August 2028 (the project will be completed when the facilities are put into service)
- Scheduled date of sending invitation for consulting services (construction supervision, etc.): April 2023
-
Publication of bids for the first procurement package through international competitive bidding for the main body of work: June 2024.