NEXCO Central Japan Tokyo Branch has been working on disaster restoration work at the Nishishon PA (off-road) of the Nishishon Bypass, which was damaged by Typhoon No. 19 in October 2019, with the goal of completing the work by the end of December 2022.
However, the completion date of the construction and the period of PA closure will be changed to around the end of April 2023 due to the longer delivery period caused by the increased demand for steel and changes in construction methods according to local conditions. In addition, continuous day and night lane restrictions between the Nishishon Ninomiya IC and Odawara IC on the Nishishon BP (off-road) will also be extended.